Home > Articles > Operating Systems, Server > Solaris

  • Print
  • + Share This
Like this article? We recommend

Functional Testing

New products are introduced to the Solaris OE Train for interoperability testing only after functional testing of the individual products is completed by the developers. As the Solaris OE Train moves along, new hardware and software components are introduced into the test process by the various business unit and development groups—Enterprise Server Product Group (ESPG), Work Group Server (WGS), Desktop Products (DT), Network Systems (NWS), Data Center High Performance Group (DHPG), VERITAS, Oracle, Sun ONE, Sun Clusters, and Network Appliance and Security Group ((NAS)–third party products).

The Test Process

FIGURE 1 shows a high level view of the Solaris OE Train test process used by Sun's Central Systems Test Quality Assurance (QA) group. TABLE 1 lists the test areas.

Figure 1FIGURE 1 Solaris OE Train Testing Flow Diagram

TABLE 1 Test Areas

Configuration

Tests hardware and software configurations.

Networking

Tests network components and software.

Operating Environment Regression

Performs regression testing on the Solaris operating environment.

Storage

Tests storage components and software.

Sun Clusters

Tests Sun Cluster software.


  • + Share This
  • 🔖 Save To Your Account