Setting Up Your Project’s Calendars

Project 2013 uses calendars that identify working times to determine when resources in your organization are likely available to work on tasks in your project.

There are four types of calendars:

  • Base calendars: Project uses base calendars as a starting point for creating the other three types of calendars (project, task, and resource calendars). You can think of them as templates upon which other calendars are based. Use base calendars to enter things like holidays, typical working hours, or other organization-wide calendar items. When you enter a holiday or a change to working times in a base calendar, those changes are automatically reflected in all other calendars that use that base calendar
  • Project calendars: The project calendar sets the default working times for all tasks in your project. For example, if most of the work on your project happens between 8 a.m. and 5 p.m. Monday through Friday, the out-of-the-box Standard calendar is the best choice for your project calendar.
  • Resource calendars: Use resource calendars to track the schedules of individual resources. For example, if a resource has a flexible work arrangement and works four 10-hour days instead of five 8-hour days, you can set that resource’s calendar to reflect that schedule without changing the overall schedule for all other resources in the organization.
  • Task calendars: Task calendars are not often used by newcomers to Project, but they can be very powerful. Use task calendars to enter special days specific to individual tasks in your project. For example, if the task must happen over a weekend but your project calendar specifies weekends as nonworking time, you can use a task calendar to call out that weekend as working time for just that task while leaving the rest of the project using the normal project calendar.

Modifying an Existing Base Calendar

Project comes with three base calendars already configured:

  • Standard: 8 a.m. to 5 p.m. weekdays, with a 1-hour lunch break
  • 24 Hours: 8 a.m. to 4 p.m., 4 p.m. to 12 a.m., and 12 a.m. to 8 a.m., continuously, with no breaks
  • Night Shift: 11 p.m. to 8 a.m. weekdays, with a 1-hour break

You can modify these base calendars to meet your organization’s needs.

To choose which base calendar you want to modify, complete these steps:

  1. On the Project tab, in the Properties group, click Change Working Time.
  2. Click the For calendar list, and then click the base calendar you want to modify.
  3. Review the working times displayed on the right portion of the Change Working Time dialog box. Click a day on the calendar to review its working times, as shown in Figure 3.7.

    FIGURE 3.7

    FIGURE 3.7. Working times are displayed for the selected calendar day.

While on the Change Working Time dialog box, you can make several different kinds of changes to the selected base calendar.

Changing a Working Day to a Nonworking Day

To change a working day to a nonworking day (for example, to add a company holiday), complete these steps:

  1. Click the day of the holiday in the calendar.
  2. Type the name of the holiday in the Name column on the Exceptions tab, and then press Tab. By default, the Start and Finish fields for the exception are set to the days you have selected in the calendar control at the top of the dialog. If those are not the dates you want, you can enter the desired dates.
  3. Double-click the holiday, and then click Nonworking on the Details dialog box.
  4. If the holiday is observed on a regular basis, you can set a Recurrence pattern and Range of recurrence.
  5. Click OK to add the holiday to the selected base calendar.

Changing a Nonworking Day to a Working Day

To change a nonworking day to a working day (for example, for an event occurring over a weekend), complete these steps:

  1. Click the day of the event in the calendar.
  2. Type the name of the event in the Name column on the Exceptions tab, and then press Tab. By default, the Start and Finish fields for the exception are set to the days you have selected in the calendar control at the top of the dialog. If those are not the dates you want, you can enter the desired dates.
  3. Double-click the event, and then click Working times on the Details dialog box.
  4. Select the Working times radio button at the top of the Details dialog.
  5. Use the From and To columns to define the working hours for the event (see Figure 3.8).

    FIGURE 3.8

    FIGURE 3.8. Set the working times for your new working day.

  6. If the event is scheduled on a regular basis, you can set a Recurrence pattern and Range of recurrence.
  7. Click OK to add the event to the selected base calendar.

Changing Default Working Times

To change the default working times for the base calendar, complete these steps:

  1. Click the Work Weeks tab, and then double-click [Default].
  2. Click a day of the week in the Select day(s) box, or use Ctrl-click or Shift-click to select multiple days, and then choose which option you want to use for scheduling on the selected days:

    • Use Project default times for these days: Click this to use the calendar options from the Project Options dialog box to define the working times on the selected days.
    • Set days to nonworking time: Click this to identify the selected days as planned days off.
    • Set day(s) to these specific working times: Click this and use the From and To columns to identify the working times for the selected days.
  3. Click OK to change the default working times for the selected base calendar.

    FIGURE 3.9

    FIGURE 3.9. Change the default working times for your base calendar.

Changing Working Times for a Specific Time Period

You may have specific weeks when the working times need to be different from the default working times. For example, if your organization has a week-long training session that limits the amount of project time to half-days for that week, you can include the schedule changes for that week in the base calendar.

To change the working times for a specific time period in the base calendar, complete these steps:

  1. Click the Work Weeks tab, and then type a name for the changed period of working time in the Name column.
  2. Choose the start time for the changed period in the Start column, and then choose the finish time in the Finish column.
  3. Double-click the row you just created to bring up the Details dialog box.
  4. Click a day of the week in the Select day(s) box, or use Ctrl-click or Shift-click to select multiple days, and then choose which option you want to use for scheduling on the selected days:

    • Use Project default times for these days: Click this to use the calendar options from the Project Options dialog box to define the working times on the selected days.
    • Set days to nonworking time: Click this to identify the selected days as planned days off.
    • Set day(s) to these specific working times: Click this and use the From and To columns to identify the working times for the selected days.
  5. Click OK to add the changed working times to the selected base calendar.

Creating a New Base Calendar

If none of the default base calendars meet your needs, you can create a new base calendar to use as a starting point for the project, task, and resource calendars.

To create a new base calendar, complete these steps:

  1. On the Project tab, in the Properties group, click Change Working Time.
  2. Click Create New Calendar.
  3. Choose how you want to create the calendar:
    • Create a new base calendar: Click this to create a new calendar from scratch. Working times are set to the calendar options from the Project Options dialog box, by default.
    • Make a copy of [existing base] calendar: Click this to use an existing base calendar as a starting point for your new base calendar. Use the drop-down list to choose which base calendar you want to copy. This option can save you a ton of time if an existing calendar already has most of the settings you need.
  4. Type a name for your new base calendar in the Name box.
  5. Click OK to create your new base calendar.

Use the steps in the previous section, “Modify an Existing Base Calendar,” to do the following:

  • Change a working day to a nonworking day
  • Change a nonworking day to a working day
  • Change the default working times for the new base calendar
  • Change the working times for a specific time period in the new base calendar

Setting Up Your Project’s Calendar

When setting up your project’s calendar, you need to decide which base calendar you want to use as a starting point. If most of your tasks need to be completed during normal working hours, choose the Standard base calendar. If most of your tasks need to be completed during off hours, the Night Shift base calendar may make more sense for your project. Or, if your project needs continuous coverage, choose the 24 Hours base calendar.

Remember that when you set the project calendar you are simply choosing what the default working times will be for tasks and resources in your project. You can modify working times for individual tasks and resources to reflect exceptions to the default hours.

To set your project’s calendar, complete these steps:

  1. On the Project tab of the ribbon, in the Properties group, click Project Information.
  2. Click Calendar and choose the base calendar that you want to use for your project.
  3. Click OK.
  4. On the Project tab, in the Properties group, click Change Working Time.
  5. Ensure that the base calendar you selected in step 2 is displayed in the For calendar list.
  6. Review the working times displayed on the right portion of the Change Working Time dialog box. Click a day on the calendar to review its working times.
  7. Use the steps in the “Modify an Existing Base Calendar” section to do the following:

    • Change a working day to a nonworking day
    • Change a nonworking day to a working day
    • Change the default working times for the project calendar
    • Change the working times for a specific time period in the project calendar
  8. Click OK to save your changes.

InformIT Promotional Mailings & Special Offers

I would like to receive exclusive offers and hear about products from InformIT and its family of brands. I can unsubscribe at any time.

Overview


Pearson Education, Inc., 221 River Street, Hoboken, New Jersey 07030, (Pearson) presents this site to provide information about products and services that can be purchased through this site.

This privacy notice provides an overview of our commitment to privacy and describes how we collect, protect, use and share personal information collected through this site. Please note that other Pearson websites and online products and services have their own separate privacy policies.

Collection and Use of Information


To conduct business and deliver products and services, Pearson collects and uses personal information in several ways in connection with this site, including:

Questions and Inquiries

For inquiries and questions, we collect the inquiry or question, together with name, contact details (email address, phone number and mailing address) and any other additional information voluntarily submitted to us through a Contact Us form or an email. We use this information to address the inquiry and respond to the question.

Online Store

For orders and purchases placed through our online store on this site, we collect order details, name, institution name and address (if applicable), email address, phone number, shipping and billing addresses, credit/debit card information, shipping options and any instructions. We use this information to complete transactions, fulfill orders, communicate with individuals placing orders or visiting the online store, and for related purposes.

Surveys

Pearson may offer opportunities to provide feedback or participate in surveys, including surveys evaluating Pearson products, services or sites. Participation is voluntary. Pearson collects information requested in the survey questions and uses the information to evaluate, support, maintain and improve products, services or sites, develop new products and services, conduct educational research and for other purposes specified in the survey.

Contests and Drawings

Occasionally, we may sponsor a contest or drawing. Participation is optional. Pearson collects name, contact information and other information specified on the entry form for the contest or drawing to conduct the contest or drawing. Pearson may collect additional personal information from the winners of a contest or drawing in order to award the prize and for tax reporting purposes, as required by law.

Newsletters

If you have elected to receive email newsletters or promotional mailings and special offers but want to unsubscribe, simply email information@informit.com.

Service Announcements

On rare occasions it is necessary to send out a strictly service related announcement. For instance, if our service is temporarily suspended for maintenance we might send users an email. Generally, users may not opt-out of these communications, though they can deactivate their account information. However, these communications are not promotional in nature.

Customer Service

We communicate with users on a regular basis to provide requested services and in regard to issues relating to their account we reply via email or phone in accordance with the users' wishes when a user submits their information through our Contact Us form.

Other Collection and Use of Information


Application and System Logs

Pearson automatically collects log data to help ensure the delivery, availability and security of this site. Log data may include technical information about how a user or visitor connected to this site, such as browser type, type of computer/device, operating system, internet service provider and IP address. We use this information for support purposes and to monitor the health of the site, identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents and appropriately scale computing resources.

Web Analytics

Pearson may use third party web trend analytical services, including Google Analytics, to collect visitor information, such as IP addresses, browser types, referring pages, pages visited and time spent on a particular site. While these analytical services collect and report information on an anonymous basis, they may use cookies to gather web trend information. The information gathered may enable Pearson (but not the third party web trend services) to link information with application and system log data. Pearson uses this information for system administration and to identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents, appropriately scale computing resources and otherwise support and deliver this site and its services.

Cookies and Related Technologies

This site uses cookies and similar technologies to personalize content, measure traffic patterns, control security, track use and access of information on this site, and provide interest-based messages and advertising. Users can manage and block the use of cookies through their browser. Disabling or blocking certain cookies may limit the functionality of this site.

Do Not Track

This site currently does not respond to Do Not Track signals.

Security


Pearson uses appropriate physical, administrative and technical security measures to protect personal information from unauthorized access, use and disclosure.

Children


This site is not directed to children under the age of 13.

Marketing


Pearson may send or direct marketing communications to users, provided that

  • Pearson will not use personal information collected or processed as a K-12 school service provider for the purpose of directed or targeted advertising.
  • Such marketing is consistent with applicable law and Pearson's legal obligations.
  • Pearson will not knowingly direct or send marketing communications to an individual who has expressed a preference not to receive marketing.
  • Where required by applicable law, express or implied consent to marketing exists and has not been withdrawn.

Pearson may provide personal information to a third party service provider on a restricted basis to provide marketing solely on behalf of Pearson or an affiliate or customer for whom Pearson is a service provider. Marketing preferences may be changed at any time.

Correcting/Updating Personal Information


If a user's personally identifiable information changes (such as your postal address or email address), we provide a way to correct or update that user's personal data provided to us. This can be done on the Account page. If a user no longer desires our service and desires to delete his or her account, please contact us at customer-service@informit.com and we will process the deletion of a user's account.

Choice/Opt-out


Users can always make an informed choice as to whether they should proceed with certain services offered by InformIT. If you choose to remove yourself from our mailing list(s) simply visit the following page and uncheck any communication you no longer want to receive: www.informit.com/u.aspx.

Sale of Personal Information


Pearson does not rent or sell personal information in exchange for any payment of money.

While Pearson does not sell personal information, as defined in Nevada law, Nevada residents may email a request for no sale of their personal information to NevadaDesignatedRequest@pearson.com.

Supplemental Privacy Statement for California Residents


California residents should read our Supplemental privacy statement for California residents in conjunction with this Privacy Notice. The Supplemental privacy statement for California residents explains Pearson's commitment to comply with California law and applies to personal information of California residents collected in connection with this site and the Services.

Sharing and Disclosure


Pearson may disclose personal information, as follows:

  • As required by law.
  • With the consent of the individual (or their parent, if the individual is a minor)
  • In response to a subpoena, court order or legal process, to the extent permitted or required by law
  • To protect the security and safety of individuals, data, assets and systems, consistent with applicable law
  • In connection the sale, joint venture or other transfer of some or all of its company or assets, subject to the provisions of this Privacy Notice
  • To investigate or address actual or suspected fraud or other illegal activities
  • To exercise its legal rights, including enforcement of the Terms of Use for this site or another contract
  • To affiliated Pearson companies and other companies and organizations who perform work for Pearson and are obligated to protect the privacy of personal information consistent with this Privacy Notice
  • To a school, organization, company or government agency, where Pearson collects or processes the personal information in a school setting or on behalf of such organization, company or government agency.

Links


This web site contains links to other sites. Please be aware that we are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of each and every web site that collects Personal Information. This privacy statement applies solely to information collected by this web site.

Requests and Contact


Please contact us about this Privacy Notice or if you have any requests or questions relating to the privacy of your personal information.

Changes to this Privacy Notice


We may revise this Privacy Notice through an updated posting. We will identify the effective date of the revision in the posting. Often, updates are made to provide greater clarity or to comply with changes in regulatory requirements. If the updates involve material changes to the collection, protection, use or disclosure of Personal Information, Pearson will provide notice of the change through a conspicuous notice on this site or other appropriate way. Continued use of the site after the effective date of a posted revision evidences acceptance. Please contact us if you have questions or concerns about the Privacy Notice or any objection to any revisions.

Last Update: November 17, 2020